US Green Building Council LEED AP Building Design + Construction LEED-AP-BD+C Exam Practice Test

Page: 1 / 14
Total 305 questions
Question 1

A new school with a 20 car parking lot has set aside four preferred parking spaces for green vehicles. What else must the project team provide to achieve Location and Transportation Credit, Green Vehicles?



Answer : D

The correct answer is D, provide qualifying electrical vehicle supply equipment in 2% of all parking spaces. According to the LEED v4 Reference Guide for Building Design and Construction, the Location and Transportation Credit, Green Vehicles, requires that projects provide preferred parking for green vehicles for 5% of the total vehicle parking capacity of the site. Green vehicles are defined as vehicles that achieve a minimum green score of 40 on the American Council for an Energy Efficient Economy (ACEEE) annual vehicle rating guide1 In addition, projects must provide one of the following:

Install alternative-fuel fueling stations for 3% of the total vehicle parking capacity of the site. Alternative fuels are defined by the U.S. Energy Policy Act of 1992 and include biodiesel, electricity, ethanol, hydrogen, natural gas, and propane.

Install electrical vehicle supply equipment (EVSE) for 2% of the total vehicle parking capacity of the site. EVSE must be Level 2 or higher as defined by SAE International's J1772 standard.

Provide a discounted parking rate of at least 20% for green vehicles. The discounted rate must be available to all customers (not limited by time of day or user groups), publicly posted at the entrance of the parking area, and included in all marketing materials for the parking facility1

In this case, the project team has provided preferred parking for green vehicles for 20% of the total vehicle parking capacity of the site (4 out of 20 spaces), which exceeds the minimum requirement of 5%. However, they still need to provide one of the additional options listed above to achieve the credit. The most feasible option for a school project with a small parking lot would be to install EVSE for 2% of all parking spaces, which would be equivalent to one space. Therefore, answer D is correct.

The other answers are incorrect because they do not meet the credit requirements. Answer A is incorrect because providing preferred parking alone is not sufficient to achieve the credit; one of the additional options must also be provided. Answer B is incorrect because providing bike racks is not relevant to this credit, which focuses on green vehicles; bike racks are part of another credit, Location and Transportation Credit, Bicycle Facilities. Answer C is incorrect because providing an additional parking space for a low-emitting and fuel-efficient vehicle would not increase the percentage of preferred parking above 20%, which is already more than enough; moreover, low-emitting and fuel-efficient vehicles are defined differently from green vehicles in LEED v4 and have their own credit, Location and Transportation Credit, Reduced Parking Footprint1 Reference: 1: LEED v4 Reference Guide for Building Design and Construction, Location and Transportation Credit: Green Vehicles, page 467.


Question 2

For Indoor Environmental Quality Credit, Construction Indoor Air Quality Management Plan, which of the following

items is required for credit compliance?



Question 3
Question 4

A project team compares a life-cycle assessment (LCA) model to a baseline design to determine the reductions in six impact categories. One impact category exceeds the baseline by 7%. Which alternative analyses should the team run to check different impact measurements?



Answer : B

This alternative analysis can help the team check the impact of reducing the amount of concrete used in the building, which can affect several impact categories, such as global warming potential (GWP), acidification, and eutrophication1. Concrete is a material with high embodied energy and carbon emissions, and reducing its use can lower the environmental impact of the building2. Optimizing the slab depth can also improve the thermal performance and daylighting of the building, which can reduce the operational energy use and demand3.


Question 5

An office is relocating to a new facility. Any furniture that is relocated to the new site can contribute as a reused material for Materials and Resources Credit, Building Product Disclosure and Optimization - Sourcing of Raw Materials if it was purchased:



Answer : A

Detailed

To qualify as reused material under the Materials and Resources Credit, furniture must have been purchased at least two years prior to the project's registration date. This ensures that the materials meet the definition of reuse, aligning with LEED's goal of reducing the demand for new materials and promoting the conservation of resources.


Question 6

What are the three phases within the Integrative Process Credit, Integrative Process?



Answer : A

The Integrative Process credit requires the project teams to perform analyses for both energy- and water-related systems from the predesign phase to the design and construction phase. The project teams should also identify and use opportunities to achieve synergies across disciplines and building systems.


* LEED Integrative Process Credit Explained - Projectific, Inc.

* CI-v4 IPc1: Integrative process | LEEDuser

* The Integrative Process in LEED V4 --- ArchEcology

* New LEED Integrative Process Credit Encourages Design-Build

Question 7
Page:    1 / 14   
Total 305 questions