US Green Building Council LEED AP Building Design + Construction LEED-AP-BD+C Exam Questions

Page: 1 / 14
Total 443 questions
Question 1

What is a viable strategy for optimizing open space under Sustainable Sites Credit, Open Space? U



Answer : D

Coordinating open space features early during the site planning phase is a viable strategy for optimizing open space under Sustainable Sites Credit, Open Space. This can help to preserve natural habitats, reduce heat island effects, and enhance human health and well-being. The credit requires that the project provide outdoor space that is at least 30% of the total site area, and that at least 25% of that outdoor space meets certain criteria for vegetated, pervious, or shaded areas.Reference:

LEED credit library: This is the USGBC's comprehensive listing of all the LEED credits available in pursuing certification for your project. The credit library contains the requirements and guidance for each credit, as well as the web-based reference guide for the Building Design and Construction rating system.

Open Space: This is the specific credit page for the Open Space credit under the Sustainable Sites category. It provides the intent, requirements, and strategies for achieving the credit, as well as the number of points available and the applicable project types.

Step by Step Approach to Comply with the Open Space Credit inLEED V5: This is a blog post that explains the steps and calculations involved in complying with the Open Space credit. It also provides some examples and tips for optimizing open space design.


Question 2

Which of the following buildings meets the Minimum Program Requirements for LEED certification?



Answer : D

The Minimum Program Requirements (MPRs) for LEED certification are:

MPR 1: Must be in a permanent location on existing land

MPR 2: Must use reasonable LEED boundaries

MPR 3: Must comply with project size requirements

Option A does not meet MPR 1 because it is located on a previously undeveloped site, which is not considered existing land. Option B does not meet MPR 3 because it is a parking garage, which is excluded from LEED certification unless it is part of a larger project. Option C does not meet MPR 1 because it is a mobile clinic, which is not considered permanent. Option D meets all the MPRs because it is a permanent building on existing land, it has reasonable LEED boundaries, and it meets the minimum gross floor area of 1,000 ft2 (93 m2) for BD+C projects.

:

LEED minimum program requirements

Minimum Program Requirements (MPRs)

What do the LEED Minimum Program Requirements Really Mean?


Question 3

A newly constructed school has installed solar thermal systems and wind turbines on site. To achieve the maximum number of Energy and Atmosphere points, which team members must be included?



Answer : C

To achieve the maximum number of Energy and Atmosphere points, the project team must include an energy modeler and a commissioning agent.The energy modeler is responsible for performing the whole-building energy simulation that demonstrates the energy performance improvement over the baseline building, which is required for Energy and Atmosphere Prerequisite 2 and Credit 11.The commissioning agent is responsible for verifying that the building's energy systems are installed, calibrated, and perform according to the owner's project requirements, basis of design, and construction documents, which is required for Energy and Atmosphere Prerequisite 1 and Credit 31.The commissioning agent also ensures that the renewable energy systems are properly integrated and functioning2. The contractor and the construction manager are not directly involved in the energy modeling or commissioning process, although they must follow the design specifications and coordinate with the commissioning agent. The facilities manager is not required for achieving the Energy and Atmosphere points, although they may benefit from the training and documentation provided by the commissioning agent.Reference:

LEED V5for Building Design and Construction, p.361

Understanding Integrative Design inLEED V5, p.92


Question 4

In order to achieve Indoor Environmental Quality Credit, Quality Views the project team increased the window-to-wall

ratio. Which prerequisite was impacted by this action?



Answer : A

The correct answer isA. Energy and Atmosphere Prerequisite, Minimum Energy Performance. This is because:

Increasing the window-to-wall ratio (WWR) would reduce the solar heat gain and the cooling load of the building, which are two of the main factors that affect the energy performance of a building12.

The WWR is defined as the ratio of the area of windows to the area of external walls in a building3.The higher the WWR, the more natural light and ventilation can be achieved, which can improve the indoor environmental quality (IEQ) and reduce the need for artificial lighting and mechanical systems4.

The LEED AP BD+C V4 credit for IEQ requires thatbuildings have a minimum WWR of 15% for south-facing walls and 20% for north-facing walls5.However, this minimum WWR may not be sufficient to achieve optimal IEQ in hot regions, where high solar radiation and humidity levels create high cooling demand6. Therefore, increasing the WWR beyond these minimum values can help achieve better IEQ by reducing both solar heat gain and cooling load.

The other prerequisites are not impacted by increasing the WWR.Building-level energy metering is a prerequisite that requires measuring and reporting energy use at individual building units or zones5.Fundamental refrigerant management is a prerequisite that requires ensuring proper handling, storage, use, recovery, and disposal of refrigerants used in cooling systems5.Fundamental commissioning and verification is a prerequisite that requires ensuring that all commissioning activities are documented and verified according to LEED standards5.


Question 5

Which of the following is required to earn Energy and Atmosphere Credit, Renewable Energy Production if using a Solar Photovoltaic System?



Answer : D

The Energy and Atmosphere Credit, Renewable Energy Production rewards projects that use renewable energy systems to offset building energy costs1.According to the LEED Reference Guide for Building Design and Construction2, the credit has two options: Option 1. On-Site Renewable Energy and Option 2. Off-Site Renewable Energy. Option 1 requires the project to use renewable energy systems that are located on the project site and that produce electricity or thermal energy for the project. The amount of renewable energy production is calculated based on the percentage of the annual energy cost that is offset by the renewable energy systems. Option 2 requires the project to use renewable energy systems that are located off the project site and that are owned by the project or have a long-term contract with the project. The amount of renewable energy production is calculated based on the percentage of the annual energy use that is offset by the renewable energy systems.

Therefore, among the given options, only Option D is relevant to the credit requirements, as it implies that the solar photovoltaic system is located on the project site and that the produced electricity is consumed by the project. The other options, such as carbon offsets, daylighting strategies, and passive solar strategies, are not directly related to the credit requirements, although they may have other benefits for the project.


Renewable Energy Production | U.S. Green Building Council

LEED Reference Guide for Building Design and Construction v4

Solar Photovoltaic Technology Basics | Department of Energy

Photovoltaic system - Wikipedia

Question 6

Which of the following projects is eligible to pursue the Energy and Atmosphere Prerequisite, Minimum Energy Performance, Option 2. Prescriptive Compliance: ASHRAE 50% Advanced Energy Design Guide?



Answer : C

The Energy and Atmosphere Prerequisite, Minimum Energy Performance, Option 2. Prescriptive Compliance: ASHRAE 50% Advanced Energy Design Guide allows projects to follow the recommendations of the ASHRAE 50% Advanced Energy Design Guides (AEDGs) for different building types and climate zones.The AEDGs provide design guidance for buildings that use 50% less energy than those built to the requirements of the ANSI/ASHRAE/IES Standard 90.1-2004 commercial code1. However, not all building types and sizes are covered by the AEDGs.According to the LEED Reference Guide for Building Design and Construction2, the following building types and sizes are eligible for this option:

Small to Medium Office buildings up to 100,000 ft2 (9 290 m2)

Medium to Large Retail buildings up to 100,000 ft2 (9 290 m2)

K-12 School buildings up to 200,000 ft2 (18 580 m2)

Warehouse and Distribution Center buildings up to 500,000 ft2 (46 450 m2)

Therefore, among the given options, only the school project is eligible to pursue this option, as it falls within the size limit for the K-12 School AEDG3.


LEED Reference Guide for Building Design and Construction v4

Minimum Energy Performance - ASHRAE 90.1 - 2010

ASHRAE 50% Advanced Energy Design Guide for K-12 School Buildings

Advanced Energy Design Guides | Department of Energy

Question 7

A LEED Building Design and Construction: New Construction office building's HVAC system includes hot water from a central utility plant. The central utility plant is owned and operated by a management company. The office pays a flat fee for hot water, included as part of the lease. The management company does not meter or invoice for actual hot water consumption. For the project to meet the requirements for Energy and Atmosphere Prerequisite, Building-Level

Energy Metering, an energy meter must be installed for



Answer : B

An energy meter must be installed for hot water at the main service point for the project to meet the requirements for Energy and Atmosphere Prerequisite, Building-Level Energy Metering.According to theLEED V5BD+C Reference Guide, this prerequisite requires that ''all energy sources used by the building must be metered or submetered''1. The hot water from the central utility plant is an energy source used by the building, even if it is not directly paid by the office. Therefore, it must be metered at the point where it enters the building. The other options are incorrect because natural gas is not an energy source used by the building in this case, and the flat fee or the ownership of the energy source do not exempt the project from the metering requirement.

:LEED V5BD+C Reference Guide, Energy and Atmosphere Category, EAp Building-Level Energy Metering, page 569.


Page:    1 / 14   
Total 443 questions